Review Comments to Final Yucca Mountain Environmental Impact Statement

December 11, 2002



Dr. Margaret Chu
U.S. Department of Energy
Office of Civilian Radioactive Waste Management
1000 Independence Avenue
Washington, D.C.

Re: Review Comments to Final Yucca Mountain Environmental Impact Statement

Dear Dr. Chu:

Consistent with the National Environmental Policy Act (NEPA), White Pine County has reviewed the Final Yucca Mountain Environmental Impact Statement (FEIS) and offers the following comments thereto. White Pine County is submitting these comments in response to the Notice of Availability (NOA) published in the Federal Register (FR) by the Environmental Protection Agency (EPA), announcing the availability of the FEIS and the beginning the 30-day review period of the document pursuant to NEPA. The County intends for these comments to be used by DOE in developing and issuing any Record of Decision based upon the FEIS and in preparing any mitigation plans as required by the Department's own regulations for implementing NEPA (10 CFR 1021.331).

In general, White Pine County commends DOE for having considered and developed comprehensive responses to the numerous comments submitted on the Draft Yucca Mountain EIS. As a consequence, the FEIS represents an improved decision support document. The County is concerned however, that in many cases revised estimates of risk have significantly increased, yet the FEIS provides little in the way of proposals for mitigating said impacts. The possibility of the Yucca Mountain repository system, including transportation elements, going forward without mitigation of system risks is simply unacceptable. DOE must consider revised estimates of risk when developing any subsequent Records of Decision and must develop and implement related mitigation plans. As the following comments suggest, certain DOE responses to comments raise new questions and concerns.

Readers Guide and Summary; Errata Sheet, Page 9 of 15, 1st row of information, Errata
The first paragraph of this section appears to be missing text and is not understandable.

Readers Guide and Summary, Page S-2, 6th paragraph
In addition to the requirement to issue a Record of Decision noted here, DOE must make clear its intent, consistent with DOE regulations at 10 CFR 1021.331, to issue a mitigation plan.

Section 4.1.7.3.1.2; 3rd paragraph
While the number of latent cancer fatalities estimated in the exposed population has increased ten times from 0.012 to 0.12 no revision or reconsideration of methods to mitigate such exposure risk is addressed in the FEIS. Any Record of Decision must consider this greatly increased level of risk and methods to mitigate said risk must be addressed in a related mitigation plan.

Section 4.1.8; 2nd paragraph
While the dose to a maximally exposed noninvolved worker has increased by 56 percent, no revision or reconsideration of methods to mitigate such exposure risk is addressed in the FEIS. Any Record of Decision must consider this greatly increased level of risk, and methods to mitigate said risk must be addressed in a related mitigation plan.

Section 6.2.4.2.3; 9th and 11th paragraphs
While the lifetime committed dose to the maximum exposed individual from a legal-weight truck cask sabotage event has been increased 150 percent, and the risk of a fatal cancer has increased by nearly 28 percent, no revision or reconsideration of methods to mitigate such exposure risk is addressed in the FEIS. Any Record of Decision must consider this greatly increased level of risk, and methods to mitigate said risk must be addressed in a related mitigation plan.

Appendix J, Section J.1.4.1.2; 6th paragraph
While the involved worker fatality incidence rate has increased approximately 130 percent, no revision or reconsideration of methods to mitigate such exposure risk is addressed in the FEIS. Any Record of Decision must consider this greatly increased level of risk, and methods to mitigate said risk must be addressed in a related mitigation plan.

Appendix J, Section J.1.4.2.3.3; 1st bullet, 2nd paragraph
While the amount of Cesium released in the maximum reasonably foreseeable accident has been increased by nearly 85 percent, no revision or reconsideration of methods to mitigate such exposure risk is addressed in the FEIS. Any Record of Decision must consider this greatly increased level of risk, and methods to mitigate said risk must be addressed in a related mitigation plan.

Comment Response Document - 3.2 (59)
The response to this comment although helpful, does not provide much needed temporal perspectives on when DOE intends to undertake transportation related field studies; State, local and Native American government consultations; environmental and engineering analyses; and National Environmental Policy Act reviews. To enable the County to anticipate its requirements for interaction with and oversight of future DOE transportation planning initiatives, please provide an anticipated schedule for these activities. Also please indicate whether additional NEPA reviews would be in the form of environmental assessments or environmental impact statement(s).

Comment Response Document - 3.2 (69)
Does the analysis of maximum reasonably foreseeable accident as presented by DOE result in the bounding of impacts? If not, does the FEIS adequately describe the nature and consequences of accidents that might occur (low probability/high consequence events)?

Comment Response Document - 3.4 (11031)
Despite this response, it is still unclear to the County whether DOE believes that it has adequately considered legal weight trucks within the FEIS to enable use of legal weight trucks to move nuclear waste to the Yucca Mountain site. Will additional NEPA analysis be required for DOE to select legal weight trucks as a transport mode and/or to select routes along which legal weight trucks will travel through Nevada to the Yucca Mountain site?

Comment Response Document - 3.4 (12759)
The response here states, "the estimated latent cancer fatalities (evaluated in the DEIS) would likely have been greater than the fatalities reported in the Supplement". The terms "would likely have been" imply that DOE does not yet know with certainty if the flexible design evaluated in the Supplemental EIS results in greater or fewer latent cancer fatalities. A definitive assessment of the risk-benefit of the flexible design over the design evaluated in the Draft EIS is needed. Please provide the County with the results of such an assessment.

Comment Response Document - 3.9 (109)
Notwithstanding the assertion here that DOE considered relevant literature concerning perceived risk, it is noted that the White Pine County Impact Assessment Report and related supporting documents are not referenced within the FEIS. Please provide the County with an indication of which, if any, documents submitted by the County were considered by DOE in preparing the FEIS. In particular, the County impact report provides a quantification of economic and fiscal impacts relating to potential perceived risks. As described in the response, DOE admits to not knowing whether perceived risk related impacts might occur (i.e. effects on property values), yet makes no attempt to quantify or recommend relevant mitigation measures for such impacts. As a consequence, impacts related to perceived risks are likely to fall into the realm of unanticipated effects for which mitigation has not been planned. The County encourages DOE to include mitigation of effects of perceived risk in a comprehensive mitigation plan for the Yucca Mountain Project.

The response here states, "If the repository was to become operational, DOE would enter into discussions with potentially affected units of local government and consider appropriate support and mitigation measures." The County is very concerned that such discussions occur prior to the repository becoming operational so as to minimize any adverse consequences. Please provide a commitment for DOE to engage in discussions with affected units of local government to ensure that required mitigation measures are agreed to and in place prior to commencement of potential impact inducing activities.

Comment Response Document - 6.1 (146)
Because the Administration has made clear its intent for the share that nuclear energy plays of the total U.S. generating capability to remain at 20 percent, the FEIS should have included an estimate of the total amount of spent nuclear waste requiring disposal during the life of the project, assuming that nuclear energy remains 20 percent of the load. Please provide the County with an estimate of the amount of waste requiring disposal, assuming nuclear energy provides 20 percent of the Nation's needs, during the next 30 years.

Comment Response Document - 9.1 (4279)
DOE's response here admits that neither of the scenarios it chose for evaluation under the No Action Alternative is likely. NEPA does not allow for consideration of alternatives that are not likely to occur. Please reconcile DOE's use of No Action Alternatives not likely to occur with NEPA requirements relating to viable alternatives.

Comment Response Document - 8.3 (161)
Here the document states, "In addition, DOE has identified mostly rail as its preferred mode of transportation, both nationally and in Nevada." The FEIS is not conclusive however, as to whether any of the five candidate rail corridors could ultimately be developed and used. In fact, the FEIS notes that a great deal of additional corridor specific work would be required. How then can DOE reach a conclusion that mostly rail is preferred? Please provide the County with an explanation as to the factors that were considered by DOE in arriving at the mostly rail conclusion. The County would appreciate being provided the analysis of various modes which resulted in the mostly rail preference.

Comment Response Document - 8.3 (201)
DOE's commitment to identify routes at least 4 years before shipments begins is inconsistent with Appendix M in which the text there states the Regional Servicing Contractor will identify routes at least 1 to 4 years prior to use of said route. The County would appreciate a definitive clarification and commitment from DOE regarding 1) who will select routes (i.e. RSC or DOE), and 2) when routes will be identified. This response also indicates that DOE would make final route selections and provide them to the Nuclear Regulatory Commission (NRC). Please clarify why routing information is to be provided to NRC and what role DOE envisions NRC playing with respect to routing.

Comment Response Document - 8.3.1 (195)
The response here notes that using routes A or B through the County would pose risks about 1.5 times greater than using the route along I-15 through Las Vegas. This is not consistent with the text in Response 8.3.1 (4191) which observes the risks associated with using the A or B routes are about a factor of 2 larger than the routes used in the EIS (I-15). Which of these is correct?

Comment Response Document - 8.3.1 (1543)
Table J-46 Cases 5 & 6, states that should the State of Nevada designate Hwy 93 or 318 as alternate preferred routes, Ely and White Pine County could expect to see a majority of the legal-weight truck shipments from sites in the east, Midwest, and northwest United States. A vast majority of SNT shipments (~45,919) over 234 years would be diverted from Mesquite to Wendover.

DOE does transportation analyses of potential SNF and HLRW transportation routes, including Alternates A & B through White Pine County, but when asked to analyze cumulative impacts due to current LLW shipments over these same routes they reply, “Under regulations issued by the U.S. DOT (49 CFR 397.101) truck shipments of SNF and HLRW could not use a route through White Pine County. Therefore, an analysis of cumulative impacts is not necessary.” If impacts from the use of Hwy 318 were analyzed, why did DOE not consider cumulative effects of transporting SNF and HLW over this route?

Comment Response Document - 8.3.1 (4219)
Here the text states, "The affected routing authorities would consider public risk and other conditions along other routes, including emergency response capability, highway design and condition, population density, traffic conditions, etc. during the process of selecting and designating alternative preferred routes." It does not appear that DOE considered (at least in any quantified manner) each of these factors in its assessment of currently legal routes (ie: existing emergency response capability). Please provide confirmation that the DOE considered the very factors it assumes would be considered by affected routing authorities.

White Pine County appreciates DOE's recognition that use of the A and B routes through the County results in risk impacts that are "about a factor of two larger that the route used for the EIS analysis" (I-15 through Las Vegas). The County would appreciate learning what route specific factors considered by DOE (if any) result in the greater degree of risk of transporting nuclear waste through the County than through the Las Vegas area. The FEIS is not clear as to why transporting waste through the County is associated with significantly greater risk. Such clarity is very important to helping decision makers understand risks associated with alternative routes.

Comment Response Document - 8.3.1 (4240)
Here the response notes that White Pine County would be eligible for technical assistance and funds provided by Section 180(c). Previously, the FEIS and comment responses indicated that states and American Indian Tribes would be eligible. Please clarify if, and under what circumstances, White Pine County would be eligible for technical assistance and funds pursuant to Section 180(c). The County requests that DOE consider promulgating a rulemaking that makes clear under what circumstances counties such as White Pine would be eligible to receive Section 180(c) assistance and funds.

Comment Response Document - 8.7 (153)
The text here states, "If the repository was approved, DOE would discuss transport details with stakeholders, including financial support, before the start of shipments." The County would appreciate clarification as to what the term "approved" means. Does it mean passage by Congress of a resolution approving the President's nomination of the Yucca Mountain site, approval by NRC of a license to construct the repository, or some other approval?

Comment Response Document - 8.7 (3427)
How does the contractor developed transportation plan referred to here relate to DOE's commitment to transportation planning described in Comment Response 8.7 (153) that is addressed above? Would the contractor also be required to discuss transportation plan details (ie: locations of emergency parking areas) with stakeholders?

Comment Response Document - 8.8.2 (4300)
The County appreciates DOE's commitment to work with local communities and tribal nations to understand and mitigate potential negative perceptions of DOE operations. The County cautions, however, that the "development and presentation of factual information regarding the actual (rather than the perceived) risks..." would result in a lag between when perceived risk related impacts were to accrue and when mitigation relating to public education might become effective. Other forms of mitigation will be required and should be addressed in a comprehensive mitigation plan for the Yucca Mountain Project.

Comment Response Document - 8.8.3 (3428)
DOE's explanation that snowbirds would be evenly distributed along transportation routes at all times is not accurate. In fact, snowbirds will be concentrated along certain routes and at various locations along certain routes. As a consequence, the FEIS still does not accurately reflect the influence of snowbirds as a component of the potentially exposed population along transportation routes.

Comment Response Document 11.1 (97), 11.1 (102)
DOE does not anticipate issuing a Record of Decision because the President makes the decision to approve the site. DOE regulations (10 CFR 1021.331) require preparation of a Mitigation Action Plan when mitigation measures are identified in a Record of Decision. At this time DOE has not decided whether or not it would prepare a Mitigation Action Plan.

The County requests that DOE explain its intent to issue a Mitigation Action Plan, thereby complying with its own regulations. DOE is requested to ensure that the Mitigation Action Plan will be prepared separately from any document prepared for the NRC licensing process. DOE is encouraged, however, to use the mitigation plan as a basis for conditions to be included in a possible license from the NRC.

If a ROD is not issued by the President, or any other agency, and/or mitigation measures are not identified in the ROD, is the DOE still required to prepare a Mitigation Action Plan? If DOE intends to develop a Mitigation Plan, please describe how affected units of local government will be participants in the planning process.

I am hereby requesting a written response to the many questions raised in this comment letter and look forward to receiving DOE's answers.

Sincerely,

[signed]

David Provost
Chairman

pc:   Chairman, Nuclear Regulatory Commission
        Administrator, U. S. Environmental Protection Agency
        Members, Nevada Congressional Delegation
        Governor Kenny Guinn
        State of Nevada Agency for Nuclear Projects
        AULGs